APC by Schneider Electric – David Derambakhsh – 5/15/2009
Routing the Communication Cables
●
Parallel Installation —
UPSs Apart
1. Remove the bottom cable inlet plates on UPS 1 and
UPS 2
2. Run the two Pbus cables to the slots on the left side
of the enclosure and down the inside panel
3. From the lowest slot, fish out the cables from the side
panel, run the cable down through the cable inlet and
through the round hole in the bottom
4. Run the Pbus cables to UPS 2 and use the reverse
of steps 2 and 3
5. Run the Abus cable (from MBP) the same way as in
step 4 (bottom to top)
6. Re-attach the cable inlet covers
7. Fasten the cables with cable ties
UPS 1
UPS 2
Commentaires sur ces manuels